Demurrage claim time bar: how long does an owner have to file?

A cargo ship sailing under cloudy skies in rough coastal waters.

Most charterparties don't leave the demurrage time bar to chance. It's written into the clause, usually somewhere between 60 and 90 days from completion of discharge, and it's a condition precedent, not a guideline. Miss it by a day and the claim is dead, no matter how solid the laytime calculation behind it.

The question charterers actually ask is whether the clock has already started and whether the desk knows it. That's what trips people up, more than the arithmetic in the calculation itself.

Where the deadline actually comes from

There's no statutory answer here. English law doesn't impose a default time bar on demurrage claims, the charterparty does. Gencon 1994 gives owners 90 days after completion of discharge. Asbatankvoy leaves it open for the parties to insert their own number in the rider clauses. Some COAs and voyage forms run as short as 30 days, others stretch past 90 if the parties negotiated it that way.

So the first thing a demurrage desk needs is the actual clause wording for that fixture, not a rule of thumb carried over from the last cargo. "Final sailing," "completion of discharge," and "completion of discharge of the last parcel" don't always mean the same calendar day, and the clock runs from whichever one the clause specifies.

What has to arrive before the clock stops

A time bar clause rarely just says "claim within 90 days." It usually says the claim has to be submitted with supporting documentation, and lists what counts: the laytime/demurrage calculation, notice of readiness, statement of facts for each port, pumping logs or timesheets, and any letters of protest. If owners file the number on day 89 but the SOF is missing, a well-drafted clause treats that as no claim at all, with no window to fill the gap later.

This is where charterers end up doing two jobs at once. One is checking whether the claim arrived on time. The other is checking whether it arrived complete, because a late or partial document bundle is often the stronger defense than arguing the hours in the calculation. Desks that keep a standing checklist against the clause wording, port by port, catch this faster than desks reconstructing it fixture by fixture when the telex lands.

Why the deadline matters before the claim even shows up

A charterer is usually reacting to a claim that's already been built, weeks or months after the vessel sailed. By the time the owner's laytime statement lands, the anchorage delay it's based on is history. The charterer is checking someone else's version of events, not watching the exposure accumulate in real time.

The gap worth closing sits earlier than the time bar. It's the stretch between a vessel joining the anchorage queue and the agent's telex confirming how long it sat there. A daily count of vessels at anchor, tracked over time gives a charterer a running read on queue build-up at a specific port, so the exposure is visible before the paperwork catches up.

The short version

The time bar is whatever the charterparty says it is, commonly 60 to 90 days from completion of discharge, running against submission of a complete claim, not a bare number. Check the clause for that fixture, confirm the trigger date, and treat missing documentation the same way as a missed deadline. Then work on seeing the congestion building at anchor before the claim arrives, so the time bar isn't the first moment the exposure gets attention.

If tracking anchorage queues before the telex catches up sounds useful for the next fixture, that's the whole offer at Port Congestion Watch.