Letter of protest: what it is and when the master should issue one

A letter of protest is the master's written objection to something happening, or not happening, at the load or discharge port that he believes will cost the owner time or money and that he does not want to be blamed for later. It goes to the charterer, the agent, or the terminal, depending on who caused the delay, and it gets copied to owners. On its own it proves nothing in a dispute. Its job is to put the other side on notice, in writing, at the time, so that six months later when someone is reconstructing a laytime claim there's a document showing the master flagged the problem as it happened rather than inventing a grievance after the fact.
What the letter actually covers
Most letters of protest fall into a handful of recurring categories: refusal or delay in berthing after NOR has been tendered, cargo not being ready when the vessel arrives, shifting or waiting time caused by terminal congestion, delays in cargo documents, bad weather working claimed by the terminal that the master disputes, or short-loading. The letter states the fact, the time it occurred, and the master's position, nothing more. It isn't the place for argument or legal theory; that comes later from the owner's lawyers or the P&I correspondent. A protest that reads like a closing submission tends to carry less weight than one that just says what happened and when.
When the master should issue one
The general rule in the trade is: issue the protest as soon as the master becomes aware of the delay or the event that's going to cost laytime, not at the end of the port call when someone back at the office asks for one. A protest dated after the vessel has sailed looks like an afterthought, and arbitrators treat it that way. If NOR is tendered and the berth isn't available, that's a protest moment. If the terminal won't start cargo operations once alongside, that's another. If the agent reports a delay but gives a reason the master doesn't accept, the protest should say so at the time, not retroactively. Masters who wait for head office instructions before protesting usually end up protesting too late to matter.
It's also worth noting the protest doesn't need to be accepted or signed by the other side to be valid. Agents and terminal reps will sometimes refuse to sign, which is itself worth noting in the vessel's log and in the master's cover note, but a refusal to acknowledge receipt doesn't undo the fact that the protest was tendered.
How it fits with NOR and the statement of facts
A letter of protest doesn't stand alone. On its own, a dispute over who caused a delay comes down to the master's word against the agent's, and that rarely settles cleanly. What makes a protest useful is the paper trail around it: the notice of readiness showing when the vessel was in fact ready to load or discharge, the statement of facts showing the hour-by-hour log of events at the berth and at anchor, and the protest itself tying the two together with the master's contemporaneous account of why they don't line up. A charterer or owner trying to run a demurrage calculation without all three is working from an incomplete file, and the first thing a P&I club or an arbitrator asks for in a dispute is exactly this set of documents, cross-checked against each other for inconsistency.
Where this gets harder is the anchorage stretch before NOR is even tendered. The statement of facts records when the vessel arrived, but whether the queue outside the port was two ships or twenty on a given day isn't something the agent's telex usually captures in a way a charterer can verify independently. That's the gap a running count of vessels at anchor over time fills, giving a charterer an outside check on congestion claims rather than relying solely on the port's own account. Port Congestion Watch builds that count from repeat satellite passes over the anchorage, so you've got your own record of queue build-up alongside the master's protests and the statement of facts, not just the agent's version of events.
If you're assembling evidence for a demurrage dispute and want an independent read on what the anchorage actually looked like that week, that's what we track.